Here’s a quick and dirty way of solving. Point where the two NPV profiles intersect will give you the crossover rate. To plot any curve you need at least 3 points. So we will work towards approximately sketching the two NPV profiles and you need “3 points” to complete a curve.
From the given question this is how you get those 3 points:
1. sum of undiscounted cash flows
project 1: (0,44) —–> (discount rate, NPV)
project 2: (0,75)
2. From the IRR information
project 1: (16.37,0)
project 2: (15.02,0)
3. From NPV @ 10% required rate of return
project 1: (10,14.12)
project 2: (10,19.53)
roughly plot these points and draw the curve for 2 projects. You will see they intersect at a point between 10% and 15.02%.
The explanation looks lengthy but when you do it, its fairly quick.