Hello,
Does anyone have an intuitive way of calculating delay (slippage) costs when breaking down the implementation shortfall method? I just cannot seem to get this to stick in a logical way… actually have found it easier calculating the entire shortfall overall and then subtracting each other component to arrive at this :/
As an example, I’m looking at Reading 39 p. 52 Q11(B) - method they use to calculate it (particularly a zero figure for the ‘Monday’ period I’m finding confusing)
Thanks
Does anyone have an intuitive way of calculating delay (slippage) costs when breaking down the implementation shortfall method? I just cannot seem to get this to stick in a logical way… actually have found it easier calculating the entire shortfall overall and then subtracting each other component to arrive at this :/
As an example, I’m looking at Reading 39 p. 52 Q11(B) - method they use to calculate it (particularly a zero figure for the ‘Monday’ period I’m finding confusing)
Thanks