vgmalu wrote:
krokodilizm wrote:
vgmalu wrote:
krokodilizm wrote:
This is a misleading question. It tries to convey the message that the further away in time a cash flow the smaller its value when discounted back to present. So a bigger discount will make cash outflows in Y4-Y6 even smaller and hence increase NPV. However it neglects the fact that with increasing discount rates ALL cash flows will reduce in value, including cash inflows.
I would say, no.
This question is about deferring outflows later in the life of the project so as to take advantage of the opportunity cost of using those funds now for a more productive use. The discount rate resembles more like the return that you can earn on those funds (outside of the project i.e. similar to opportunity cost of letting go of the investment opportunity of investing in this capital project).
High the return required (discount rate) on the outflow, lower the PV of the outflow and higher the NPV, because by deferring the investments into the project you are able to achieve higher return (from more productive use of those funds now.)
About your second question, about the “PV of inflows getting lower as well”, the net impact is in favor of outflow because outflows are happening later in the life of the project and hence it has greater no. of discounting periods as well (thats why i said, think of it as the benefit of holding onto those funds and investing more productively out of the project), so this combination leads to
lowest discounted value of the outflow and
not as low discounted value of the inflows. Overall result - Increase in NPV
You must be really dumb not to refer to the graph which depicts my point that NPV as a function of discount rate is ambiguous. Go back to the original post: “ For
an investment (not two investments) that has inflows in the early stages and outflows in the later stages, the use of a
higher discount rate makes the
NPV higher.” Except it doesn’t…
If you like to think differently fair enough. That’s what I said. The questions is misleading and ambiguous, subject to different interpretations.
BTW i could not really see the graph that you had posted earlier(some error was coming instead of the graph), anyways I still stand by what i said earlier.
I suppose what your interpretation is,
When all else remaining same how can the project’s NPV increase if Discount rate increases? or How can the NPV increase when the WACC is increasing(in the special situation where cash inflows into the project are at later stage)?
so to answer this and eliminate all confusion, lets define something
inflow means -> the funds invested by co. into the project
outflow means -> cash flows generated by the project
Now lets imagine, the inflow as something which the co. borrows from a bank, and bank charges WACC as the interest taking into consideration riskiness of the project. The benefit of having inflow at the later stage of the project is to defer borrowing at a later stage and save the interest. If the WACC increases, the Bank will fund at a higher rate, by deferring the funding at a later stage, you are drawing more and more interest benefits, you need to pay to the bank only at a later stage (the benefit also increases because of WACC increasing)
The outflow out of the project come at a earlier stage though. The benefit of deferring the inflow outweighs the disadvantage of discounting of outflows out of the project on relative terms. This relative advantage increases further as discount rate goes up (WACC).