when you are calculating the NPV of a project where there is a chance of failure, what is the correct formula? I’ve come across these 3 (i.e. questions 9, 10, and 28 from reading 66) and can’t seem to understand what the question is asking that would require the change in formula:
Ps: Probablility of success
Pf: Probability of Failure
C0: Original cash outlay at t=0
expected NPV = Ps* NPV of future cash flows (not counting C0) if successful + Pf * NPV of future cash flows (not counting C0) if unsuccessful - C0
or,
Expected NPV = Ps * NPV of all cash flows (including C0) if successful + Pf * NPV of future cash flows (including C0) if unsuccessful
or,
Expected NPV = Ps * NPV of future cash flows (not counting C0) if successful - C0
Any help?
Ps: Probablility of success
Pf: Probability of Failure
C0: Original cash outlay at t=0
expected NPV = Ps* NPV of future cash flows (not counting C0) if successful + Pf * NPV of future cash flows (not counting C0) if unsuccessful - C0
or,
Expected NPV = Ps * NPV of all cash flows (including C0) if successful + Pf * NPV of future cash flows (including C0) if unsuccessful
or,
Expected NPV = Ps * NPV of future cash flows (not counting C0) if successful - C0
Any help?