archived_user
New member
- Dec 7, 2011
- 0
- 0
Question: Should the company accept a project that has an IRR of 14% and an NPV of $2.8m if the cost of capital is 12%
A. Yes, based only on the NPV
B. Yes, based on the NPV and the IRR
C. No, based on both the NPV and the IRR
I selected A because I think if NPV>0, then apparrently, IRR will be larger than cost of capital. But the answer by Kaplan is B. I do not understand the rational behind. Could somebody kind enough to explain?
A. Yes, based only on the NPV
B. Yes, based on the NPV and the IRR
C. No, based on both the NPV and the IRR
I selected A because I think if NPV>0, then apparrently, IRR will be larger than cost of capital. But the answer by Kaplan is B. I do not understand the rational behind. Could somebody kind enough to explain?